Connect with us

I&B Ministry

MIB criticised for violating contractual norms for national film museum construction

Published

on

NEW DELHI: The Ministry of Information and Broadcasting (MIB) failed to secure compliance with provisions of the contract before releasing advance payments to National Buildings Construction Corporation for the National Museum on Indian Cinemas (NMIC) leading to blocking of funds while the intended objective of commissioning the Museum for public remained unfulfilled.

 

Rejecting the reasons given by the Ministry, the Comptroller and Auditor General has said in its latest report that the Ministry prematurely released payments without observing linkages with various milestones of construction activity and their completion. 

Advertisement

 

Out of a total sum of Rs 88.11 crore released to NBCC between March 2010 and March 2011, only Rs 36.72 crore had been utilised leading to blocking of substantial sum with the NBCC.

 

Advertisement

CAG said there was no provision of advance payment except payment on signing of contract between the Ministry and the NBCC.

 

The Films Division of the Ministry had in 2010 initiated a project on turnkey basis of constructing the NMIC in the Films Division Complex at Mumbai proposed to be commissioned for public during the centenary year of Indian Cinemas in 2013. 

Advertisement

 

Under the contract, the estimated cost of work was Rs 101.20 crore with expected date of completion being June 2012. 

 

Advertisement

Under clause 7 of the contract, the payment to NBCC was to be based on actual cost of all the works of the project and it included all the costs as paid to contractors/suppliers etc. Payments to NBCC were to be released on completion of various milestones as specified in the contract. 

 

NBCC had to submit report for requirement of funds and while submitting the invoice it had to certify that it had completed the activity as per schedule. In terms of clause 10 of the contract, NBCC had to submit quarterly report indicating physical and financial progress of the work.

Advertisement

 

The CAG examination of records disclosed that the Ministry in contravention of the terms of contract, released funds to NBCC without linkages with the specific milestones as provided in the contract. It also did not ascertain the actual progress of work before releasing payments.

 

Advertisement

CAGt also observed that the required statutory approval from Municipal Corporation of Greater Mumbai was obtained by the Ministry only in August 2013. The Ministry had thus released more than 85 per cent of the estimated project cost (Rs 88 crore out of Rs 101 crore) even before obtaining the required statutory approval.

 

It was also noted that NBCC could incur expenditure of only Rs 36.72 crore out of released amount of Rs 88.11 crore as of December 2014, resulting in blocking of substantial sums for different durations during the period March 2010 to December 2014.

Advertisement

 

When this was pointed out, the Ministry said in February this year that since the project was to be completed before Centenary Celebration of Indian Cinema in 2013, the Ministry had relaxed/modified the milestones of construction of NMIC, before releasing the funds to NBCC through FD. It also said the NBCC opened a separate Bank Account for the NMIC project. The bank interest was being credited to that account. 

 

Advertisement

The construction work of the Museum was in progress and according to the revised timeline for completion, the Museum was to be completed and handed over by December 2015.

 

But CAG noted that the reply of the Ministry did not address the issue of premature release of funds without synchronising the payments with the progress of work. 

Advertisement

 

Furthermore, the fact remained that the Ministry failed to secure compliance with the provisions of the contract before releasing advance payments to NBCC leading to blocking of funds while the intended objective of commissioning the National Museum on Indian Cinemas for public remained unfulfilled.

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

I&B Ministry

Prasar Bharati opens AIR to private content under new policy

NIPP introduces revenue share, sponsored and gratis models

Published

on

MUMBAI: Radio may be the oldest voice in the room, but it’s learning some very modern tricks. In a bid to stay tuned to changing listener habits, Prasar Bharati has opened the doors of All India Radio to private players under a newly rolled-out content framework. The initiative, titled Notice Inviting Programme Proposals (NIPP), marks a significant shift in how the public broadcaster approaches programming moving from a largely in-house model to a more collaborative, market-aligned ecosystem. Issued by Akashvani’s Directorate General in April 2026, the policy invites private producers, content owners and aggregators to pitch programmes across formats, from radio dramas and documentaries to quiz shows, storytelling and music-led content.

At the heart of the framework lies a three-pronged participation model designed to balance creative freedom with commercial viability. The most prominent route is revenue sharing, where advertising and sponsorship income generated by a programme is split between the producer and the broadcaster. The structure tilts in favour of creators offering a 70:30 split when producers bring in advertising, and 65:35 when monetisation is handled by Prasar Bharati.

Alongside this sits the sponsored model, where producers fully fund and monetise their content, subject to compliance with advertising norms and the AIR Broadcast Code. For those less commercially inclined, a gratis route allows content to be submitted free of cost, with Prasar Bharati retaining all monetisation rights effectively turning the platform into a national distribution channel for diverse voices.

Advertisement

The move comes as legacy media grapples with intensifying competition from private FM networks, streaming platforms and digital audio ecosystems. By repositioning AIR as both a public service broadcaster and a content marketplace, Prasar Bharati appears to be recalibrating its role in a rapidly evolving media landscape.

Importantly, the framework does not dilute editorial control. All submissions must adhere to the AIR Broadcast Code, and proposals are evaluated through a layered process that weighs storytelling quality, production capability, audience appeal and revenue potential. Only proposals crossing a defined threshold move forward, signalling that while access has widened, the bar remains firmly in place.

Operational discipline is another cornerstone of the policy. Producers are required to maintain broadcast-ready content, deliver episode banks in advance and navigate a structured approval process. Crucially, all production costs are borne by the content provider, reinforcing Prasar Bharati’s positioning as a distribution and oversight platform rather than a commissioning entity.

Advertisement

What elevates the initiative further is its scale. The framework spans multiple clusters and stations across India, covering both metro and regional markets, with specific language mandates and submission channels. This not only expands the content pipeline but also deepens linguistic and cultural representation, an area where AIR has historically held an advantage.

In effect, NIPP signals a quiet but meaningful transformation. AIR is no longer just broadcasting to the nation, it is inviting the nation to broadcast with it, blending legacy reach with contemporary content economics in a bid to stay relevant in an increasingly fragmented audio universe.

Advertisement
Continue Reading

Advertisement News18
Advertisement
Advertisement
Advertisement Whtasapp
Advertisement Year Enders

Indian Television Dot Com Pvt Ltd

Signup for news and special offers!

Copyright © 2026 Indian Television Dot Com PVT LTD