Connect with us

Applications

No value for money in BBC’s early management of digital media: NAO

Published

on

MUMBAI: The BBC Trust has published an independent report commissioned from the National Audit Office (NAO) on the BBC‘s management of its Digital Media Initiative (DMI).


The NAO has concluded that the early stages of the Programme were not value for money, mainly as a result of a 21 month delay leading to ?26 million of benefits not being achieved in the period 2009-10 to 2010-11.


The DMI is a technology transformation project designed to allow BBC staff to develop, create, share and manage video and audio content and programming on their desktop. It is intended to improve production efficiency across the BBC. The estimated gross cost of delivery and implementation to the end of March 2017 is ?133.6 million.
 
The BBC appointed its existing IT contractor (Siemens) to develop the Programme. The contract with Siemens was terminated by mutual agreement in July 2009. The BBC then took responsibility for delivery of the project in-house and was able to offset its increased costs by a ?27.5 million financial arrangement agreed with Siemens. In-house delivery of the system has started well, and, while there is a considerable way to go before the Programme is complete, users have been positive about the elements delivered thus far.


Key points from the report and the Trust‘s response to them include:


1. The way in which the BBC appointed the contractor without a new competition and was then unable to intervene effectively in system development without undermining its transfer of financial risk to the contractor was not an effective way of approaching the delivery of a complex programme.


The Trust notes that the BBC awarded the DMI contract to Siemens under a technology framework agreement intended to provide efficiencies, in part by reducing procurement costs. The Trust agrees that the decision to award the contract to Siemens did not lead to the planned outcome and the first phase of the project did not proceed according to plan. The Trust notes, however, that the BBC reached a financial arrangement with Siemens which allowed the BBC to allocate ?27.5 million to meet the increased cost of completing the delayed Programme.


2. Although once problems came to light and it took the Programme technology development in-house, the BBC did not test whether that was the best option. It also did not test the value for money of this approach despite the Programme being in difficulty and behind schedule.


The Trust closely monitored the status of the project, and was satisfied that the BBC Finance Committee (which includes the BBC Director-General, the BBC Chief Financial Officer and the BBC Chief Operating Officer) made an appropriate decision as to how to continue the DMI – given that the financial cost to the BBC was not increasing and the aims of the project remained as previously stated. However, the proposal to increase the scope of the project was rightly fully assessed and brought before the Trust in May and June 2010.


3. The financial benefits of the Programme were initially overstated. The original cost-benefit estimate in January 2008 was a projected net benefit of ?17.9 million. The latest forecast is of a net cost to the BBC of ?38.2 million by March 2017, partly offset by a ?27.5 million financial package agreed with Siemens, leading to a final net cost of ?10.7 million. 
 
The Trust noted that the financial benefits case was revised in the 2010 case, and fully agrees with the NAO‘s recommendation that greater rigour should be applied than was evident in the 2008 business case. It is reassuring that the NAO noted significant improvements in the 2010 business case. However, the non-financial benefits of DMI are also significant, and the financial benefits of DMI, while important, are only part of the picture.
BBC Trustee with lead responsibility for value for money Anthony Fry said, “The DMI is a cutting edge project that will improve the way the BBC operates and transform the way it makes programmes and content. The Trust agrees with the NAO that the early phase of the project ran into significant difficulties, but the BBC reacted with speed and efficiency, and since bringing it in-house delivery is progressing as planned. Clearly there are lessons to be learnt and the Trust will continue to monitor progress against the action plan we‘ve asked the BBC Executive to produce.”


NAO head Amyas Morse said, “The BBC‘s approach to the early stages of this Programme was disappointing and did not achieve value for money. However, since taking the Programme back in house, delivery of the system has progressed well, and users have responded positively. The real test of value for money of the Programme as a whole will be the take up by users across the BBC and elsewhere, and on this it is too early to conclude.”

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Applications

With 57 per cent single new users, Ashley Madison rebrands as discreet dating platform

Platform says majority of new members now identify as single

Published

on

INDIA: Ashley Madison is shedding the “married-dating” label that defined it for two decades, repositioning itself as a platform for discreet dating in what it calls the post-social media age.

The rebrand, unveiled in India on 27 February, 2026, marks a structural shift in business model and identity. Once synonymous with married dating, the company now describes itself as the “premier destination for discreet dating” under a new tagline: Where Desire Meets Discretion.

The pivot is data-driven. Internal figures show that 57 per cent of global sign-ups between 1 January and 31 December, 2025 identified as single: a notable departure from the platform’s married core. The company argues that its community has already evolved beyond its original positioning.

Advertisement

“In an age where our lives have been constantly put on public display, privacy has become the new luxury,” said Ashley Madison chief strategy officer Paul Keable. He framed the platform’s offering as “ethical discretion” for singles, separated, divorced and non-monogamous users seeking private connections.

The shift also taps into wider digital fatigue. A global survey conducted by YouGov for Ashley Madison, covering 13,071 adults across Australia, Brazil, Canada, Germany, India, Italy, Mexico, Spain, Switzerland, the UK and the US, found mounting discomfort with hyper-public online lives.

Among dating app users, 30 per cent cited constant swiping and messaging as a source of fatigue, while 24 per cent pointed to pressure to curate public-facing profiles and early personal disclosure. Some 27 per cent said fears of screenshots or information being shared contributed to exhaustion; an equal share cited unwanted attention.

Advertisement

The retreat from oversharing appears broader. According to the survey, 46 per cent of adults actively try to keep most aspects of their life private online. Only 8 per cent feel comfortable sharing most aspects publicly, while 35 per cent say they are becoming more selective about what they disclose.

Ashley Madison is betting that this cultural recalibration towards controlled visibility can be monetised. By doubling down on privacy infrastructure and reframing itself around discretion rather than infidelity, the company is attempting to convert reputational baggage into a premium proposition.

Advertisement
Continue Reading

Advertisement News18
Advertisement
Advertisement
Advertisement
Advertisement Whtasapp
Advertisement Year Enders

Indian Television Dot Com Pvt Ltd

Signup for news and special offers!

Copyright © 2026 Indian Television Dot Com PVT LTD

This will close in 10 seconds