| The
thrust of the liquid engines used in the strap-on stages is precisely controlled
by a set of regulators. Detailed analyses have indicated that in S4 engine the
thrust control was not effective. Instead of stabilizing at 5.85 MPa (Mega Pascal)
chamber pressure, it reached 7.11 MPa at 2.8 sec. This was much beyond the design
limits and the engine failed at 0.2 sec after lift-off, that is 5 sec after its
ignition. Simulations
and analyses of flight data and verification through calibration tests have led
to the conclusion that the propellant regulator in the failed engine had much
higher discharge coefficient in its closed condition. The reason for this could
be an inadvertent error in manufacturing, which escaped the subsequent inspection,
and acceptance test procedures. This regulator has functioned satisfactorily in
all the previous 50 engines manufactured and tested so far, states an official
release. The
larger flow of propellant led to higher operating pressure in the gas generator
(4.7 MPa against design specification of 3.6 MPa). Due to this higher operating
pressure of the gas generator, the water flow rate into it got reduced. The combined
effect of larger flow of propellants and reduced flow of water led to a very high
gas temperature of 1823 K against design specification of 900 K and pressure of
4.7 MPa against the design specification of 3.6 MPa. The very high operating pressure
and temperature resulted in the structural failure of the gas generator. The consequent
abrupt stopping of the turbo pumps that feed propellants at very high pressures
to the engines led to loss of thrust of S4 engine. The water calibration tests
conducted simulating the malfunction of the propellant regulator hardware could
closely reproduce the flight phenomenon thereby confirming the larger flow area.
FAC
has concluded that the design of GSLV is robust and recommended implementation
of strict control on fabrication, inspection and acceptance procedures. Among
others, FAC has recommended fabrication processes to be critically reviewed and
updated. It has recommended for independent inspection of all critical dimensions
of components and subassemblies by in-house agencies. Further, long duration hot
test on one out of every 20 engines fabricated has been recommended to ensure
that production process is under control. In addition, FAC has recommended strengthening
the process of clearance of launch during Automatic Launch Sequence (ALS) phase.
FAC
conclusions and recommendations have been accepted and necessary action has been
initiated to implement all of them, the release adds. |